Base
Notice2018-198482018-09-12

FirstEnergy Nuclear Operating Company (FENOC) and FirstEnergy Nuclear Generation, LLC, Beaver Valley Power Station, Units 1 and 2, Davis-Besse Nuclear Power Station, Unit No. 1, Perry Nuclear Power Plant, Unit No. 1

Nuclear Regulatory Commission

Abstract

The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a July 19, 2017 request from FirstEnergy Nuclear Operating Company (FENOC) and FirstEnergy Nuclear Generation, LLC (collectively, the licensee), as supplemented by letters dated March 16, 2018, and May 2, 2018. The exemption is from the NRC definition for a physical barrier regarding the construction standards for the fence bracket angle. The exemption allows the licensee to apply a fence topper bracket angle of zero degrees (or vertical) at specific locations on the protected area fence at each facility, in lieu of the 30 to 45 degree fence bracket angle required by Commission regulations. All other construction standards contained in the Commission regulations for a physical barrier fence topper remain applicable.

Action & Dates

Action
Exemption; issuance.
Dates
The exemption was issued on September 6, 2018.

Document Excerpt

Document Headings Document headings vary by document type but may contain the following: the agency or agencies that issued and signed a document the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to the agency docket number / agency internal file number the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details. Nuclear Regulatory Commission [Docket Nos. 50-346, 50-440, 50-334 and 50-412; NRC-2018-0187, NRC-2018-0192, and NRC-2018-0193] AGENCY: Nuclear Regulatory Commission. ACTION: Exemption; issuance. SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a July 19, 2017 request from FirstEnergy Nuclear Operating Company (FENOC) and FirstEnergy Nuclear Generation, LLC (collectively, the licensee), as supplemented by letters dated March 16, 2018, and May 2, 2018. The exemption is from the NRC definition for a physical barrier regarding the construction standards for the fence bracket angle. The exemption allows the licensee to apply a fence topper bracket angle of zero degrees (or vertical) at specific locations on the protected area fence at each facility, in lieu of the 30 to 45 degree fence bracket angle required by Commission regulations. All other construction standards contained in the Commission regulations for a physical barrier fence topper remain applicable. DATES: The exemption was issued on September 6, 2018. ADDRESSES: Please refer to Docket IDs. NRC-2018-0187, NRC-2018-0192, and NRC-2018-0193 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods: Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0187, NRC-2018-0192, and NRC-2018-0193. Address question

Read full document on FederalRegister.gov →

Related Documents

Other Federal Register documents from the same docket.

Full Document

Citation: 83 FR 46196