Record of Decision; Montana Alberta Tie Ltd.

Energy Department

Abstract

DOE announces its decision to issue a Presidential permit to Montana Alberta Tie Ltd. to construct, operate, maintain, and connect a new single-circuit 230,000-volt (230-kV) electric transmission line across the U.S.-Canada border near Cut Bank, Montana, along the preferred alternative identified in the EIS, with the environmental mitigation measures and electric reliability conditions noted below. The environmental impacts that would be associated with the line were analyzed in the Environmental Impact Statement for the Montana Alberta Tie Ltd. (MATL) 230-kV Transmission Line (DOE/EIS-0399, MATL EIS). The transmission line, known as the MATL Project, would originate at an existing NorthWestern Energy (NWE) 230-kV Switchyard at Great Falls, Montana, and extend north to a new substation to be constructed northeast of Lethbridge, Alberta, Canada. Approximately 130 miles of the 203-mile long transmission line would be constructed in the United States. In reaching this decision, DOE considered the low environmental impacts in the United States from constructing, operating, maintaining, and connecting the proposed international transmission line, the absence of adverse impacts to the reliability of the U.S. electric power supply system, the absence of major issues of concern to the public, and the favorable recommendations of the Departments of State and Defense. DOE has prepared this ROD in accordance with the regulations of the Council on Environmental Quality (40 CFR Parts 1500-1508) for implementing the National Environmental Policy Act (NEPA), and DOE's NEPA Implementing Procedures (10 CFR Part 1021).

Action & Dates

Action
Record of Decision (ROD).

Document Excerpt

Document Headings Document headings vary by document type but may contain the following: the agency or agencies that issued and signed a document the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to the agency docket number / agency internal file number the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details. Department of Energy [Docket No. PP-305] AGENCY: Office of Electricity Delivery and Energy Reliability (OE), Department of Energy (DOE). ACTION: Record of Decision (ROD). SUMMARY: DOE announces its decision to issue a Presidential permit to Montana Alberta Tie Ltd. to construct, operate, maintain, and connect a new single-circuit 230,000-volt (230-kV) electric transmission line across the U.S.-Canada border near Cut Bank, Montana, along the preferred alternative identified in the EIS, with the environmental mitigation measures and electric reliability conditions noted below. The environmental impacts that would be associated with the line were analyzed in the Environmental Impact Statement for the Montana Alberta Tie Ltd. (MATL) 230-kV Transmission Line (DOE/EIS-0399, MATL EIS). The transmission line, known as the MATL Project, would originate at an existing NorthWestern Energy (NWE) 230-kV Switchyard at Great Falls, Montana, and extend north to a new substation to be constructed northeast of Lethbridge, Alberta, Canada. Approximately 130 miles of the 203-mile long transmission line would be constructed in the United States. In reaching this decision, DOE considered the low environmental impacts in the United States from constructing, operating, maintaining, and connecting the proposed international transmission line, the absence of adverse impacts to the reliability of the U.S. electric power supply system, the absence of major issues of concern to the public, and the favora

Read full document on FederalRegister.gov →

Related Documents

Other Federal Register documents from the same docket.

Full Document

Citation: 73 FR 67860