Base
Notice2019-048212019-03-15

NextEra Energy Seabrook, LLC; Seabrook Station, Unit No. 1

Nuclear Regulatory Commission

Abstract

The U.S. Nuclear Regulatory Commission (NRC) has issued Renewed Facility Operating License No. NPF-86 to NextEra Energy Seabrook, LLC (NextEra), Hudson Light & Power Department, Massachusetts Municipal Wholesale Electric Company, and Taunton Municipal Lighting Plant. Renewed Facility Operating License No. NPF-86 authorizes NextEra to operate Seabrook Station, Unit No. 1 (Seabrook) at reactor core power levels not in excess of 3,648 megawatts thermal, and in accordance with the provisions of the Seabrook renewed operating license and technical specifications. In addition, the NRC has prepared a record of decision (ROD) that supports the agency's decision to issue Renewed Facility Operating License No. NPF-86 authorizing operations at Seabrook for an additional 20 years.

Action & Dates

Action
License renewal and record of decision; issuance.
Dates
The NRC issued Renewed Facility Operating License No. NPF-86 on March 12, 2019.

Document Excerpt

Document Headings Document headings vary by document type but may contain the following: the agency or agencies that issued and signed a document the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to the agency docket number / agency internal file number the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details. Nuclear Regulatory Commission [Docket No. 50-443; NRC-2010-0206] AGENCY: Nuclear Regulatory Commission. ACTION: License renewal and record of decision; issuance. SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued Renewed Facility Operating License No. NPF-86 to NextEra Energy Seabrook, LLC (NextEra), Hudson Light & Power Department, Massachusetts Municipal Wholesale Electric Company, and Taunton Municipal Lighting Plant. Renewed Facility Operating License No. NPF-86 authorizes NextEra to operate Seabrook Station, Unit No. 1 (Seabrook) at reactor core power levels not in excess of 3,648 megawatts thermal, and in accordance with the provisions of the Seabrook renewed operating license and technical specifications. In addition, the NRC has prepared a record of decision (ROD) that supports the agency's decision to issue Renewed Facility Operating License No. NPF-86 authorizing operations at Seabrook for an additional 20 years. DATES: The NRC issued Renewed Facility Operating License No. NPF-86 on March 12, 2019. ADDRESSES: Please refer to Docket ID NRC-2010-0206 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2010-0206. Address questions about NRC dockets in Regulations.gov to Krupskaya Castellon; telephone: 301-287-9221; email: K

Read full document on FederalRegister.gov →

Related Documents

Other Federal Register documents from the same docket.

Full Document

Citation: 84 FR 9563