General Services Administration Acquisition Regulation (GSAR); Adoption of Construction Project Delivery Method Involving Early Industry Engagement-Construction Manager as Constructor (CMc)

General Services Administration

Abstract

The General Services Administration (GSA) is issuing a proposed rule amending the General Services Administration Acquisition Regulation (GSAR) to adopt an additional project delivery method for construction, construction manager as constructor (CMc). The private sector prevalently uses this type of construction project delivery method, which allows for early industry engagement by the construction contractor to provide reduced cost growth, reduced schedule growth and administrative savings. The current Federal Acquisition Regulation (FAR) and GSAR lack detailed coverage differentiating various construction project delivery methods. GSA's policies on CMc have been previously issued through other means. By incorporating CMc into the GSAR and differentiating for various construction methods, the GSAR will provide centralized guidance that eases the burden for industry to understand and execute CMc construction contracts. Centralized guidance will also ensure consistent application of construction project principles across GSA. Additionally, integrating these requirements into the GSAR will allow industry to provide public comments through the rulemaking process.

Action & Dates

Action
Proposed rule.
Dates
Interested parties should submit written comments to the Regulatory Secretariat Division on or before January 7, 2019 to be considered in the formulation of a final rule.

CFR References

Topics

Government procurement

Public Comment

Comments Close
2019-01-07

Document Excerpt

Document Headings Document headings vary by document type but may contain the following: the agency or agencies that issued and signed a document the number of the CFR title and the number of each part the document amends, proposes to amend, or is directly related to the agency docket number / agency internal file number the RIN which identifies each regulatory action listed in the Unified Agenda of Federal Regulatory and Deregulatory Actions See the Document Drafting Handbook for more details. General Services Administration 48 CFR Parts 501, 536, and 552 [GSAR Case 2015-G506; Docket No. GSAR-2018-0013; Sequence No. 1] RIN 3090-AI81 AGENCY: Office of Acquisition Policy, General Services Administration (GSA). ACTION: Proposed rule. SUMMARY: The General Services Administration (GSA) is issuing a proposed rule amending the General Services Administration Acquisition Regulation (GSAR) to adopt an additional project delivery method for construction, construction manager as constructor (CMc). The private sector prevalently uses this type of construction project delivery method, which allows for early industry engagement by the construction contractor to provide reduced cost growth, reduced schedule growth and administrative savings. The current Federal Acquisition Regulation (FAR) and GSAR lack detailed coverage differentiating various construction project delivery methods. GSA's policies on CMc have been previously issued through other means. By incorporating CMc into the GSAR and differentiating for various construction methods, the GSAR will provide centralized guidance that eases the burden for industry to understand and execute CMc construction contracts. Centralized guidance will also ensure consistent application of construction project principles across GSA. Additionally, integrating these requirements into the GSAR will allow industry to provide public comments through the rulemaking process. DATES: Interested parties should submit written comments to the Regula